Virupaksha M Biradar
Hospet
Approved
20th May 2024
Completed
16th Mar 2024
Registration No.
PRM/KA/RERA/1669/440/PR/200524/006909
Acknowledgement No.
ACK/KA/RERA/1669/440/PR/280424/008085
Project Type
Plotted Development
District
Vijayanagara
Taluka
Hospet
State
Karnataka
| Number of Survey No./CMC No./CTS No./PID No. | 1 |
| Is there any Litigations on Land/Property/Khatha? | NO |
| Type of Firm | Proprietorship |
| Promoter Name | Virupaksha M Biradar |
| Main Objectives | Real Estate Development, Sales and Marketing |
| Trade Name | Virupaksha M Biradar |
| Registration Number | 29BAJPB5124J1ZQ |
| PAN | BAJPB5124J |
| GSTIN | 29BAJPB5124J1ZQ |
| Promoter Address | 294, 15th Ward, 1st Cross,Bharathi Nagar, Amaravathi ,Hospet ,Vijayanagara-583201 |
| District | Vijayanagara |
| Taluk | Hospet |
| PIN Code | 583201 |
| Name of Authorized Signatory | Virupaksha M Biradar |
| Is there any RERA Registrations in other State / UT ? | NO |
| Is there any Projects Launched In The Past 5 Years in Karnataka ? | YES |
| Project Name | PAMPA VIRUPAKSHESHWARA NAGAR |
| Project Description | Residential Plotted Development comprises of 96 plots of different dimensions |
| Type of Project | Plotted Development |
| Current Status | Completed |
| Is there any case pending ? | NO |
| Is Payment Pertaining to Project Land Pending ? | NO |
| Project Address | Sy No 54/8, 54/10, 56/F, 56/B2B, 56/5, 56/G, 56/1, 56/2 and 56/4 situated at Ananthashayanagudi, , Hospet Taluk , Bellari , HOSPET , Vijayanagara, Karnataka - 583203 |
| State/UT | Karnataka |
| Pin Code | 583203 |
| Present Address | 294, 15th Ward, 1st Cross, Bharathi Nagar, Amaravathi, Hospet , Vijayanagara , Karnataka - 583201 |
| Permanent Address | 294, 15th Ward, 1st Cross, Bharathi Nagar, Amaravathi, Hospet , Vijayanagara , Karnataka - 583201 |
| Official Address | 294, 15th Ward, 1st Cross, Bharathi Nagar, Amaravathi, Hospet , Vijayanagara , Karnataka - 583201 |
| Sl No. | |
| Sl No._1 |
| Type of Inventory | 12XODD |
| No of Inventory | 5 |
| Carpet Area (Sq Mtr) | 654 Sq Mtr |
| Area of exclusive balcony/verandah (Sq Mtr) | 0 Sq Mtr |
| Area of exclusive open terrace if any (Sq Mtr) | 0 Sq Mtr |
| Sl No. | Plot No. | Plot Type | Plot Size | Plot Area | Phase | Stage | North Dimension | South Dimension | East Dimension | West Dimension | North Schedule Dimension | South Schedule Dimension | East Schedule Dimension | West Schedule Dimension |
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | 1 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 2 | SY NO 127 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 2 | 2 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 3 | PLOT NO 1 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 3 | 3 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 4 | PLOT NO 2 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 4 | 4 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 5 | PLOT NO 3 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 5 | 5 | Residential | ODD SIZE | 222.44 | Stage 2 | Completed | 15 | 15 | 15.7 | 15.8 | ROAD | PLOT NO 4 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 6 | 6 | Residential | 12*15 | 180 | Stage 2 | Completed | 12 | 12 | 15 | 15 | PLOT NO 7 | ROAD | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 7 | 7 | Residential | 12*15 | 180 | Stage 2 | Completed | 12 | 12 | 15 | 15 | ROAD | PLOT NO | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 8 | 8 | Residential | 12*15 | 180 | Stage 2 | Completed | 12 | 12 | 15 | 15 | PLOT NO 9 | ROAD | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 9 | 9 | Residential | 12*15 | 180 | Stage 2 | Completed | 12 | 12 | 15 | 15 | ROAD | PLOT NO 8 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 10 | 10 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 11 | ROAD | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 11 | 11 | Residential | 12*ODD | 176.25 | Stage 2 | Completed | 15 | 15 | 11.5 | 12 | ROAD | PLOT NO 10 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 12 | 12 | Residential | ODD SIZE | 171.25 | Stage 2 | Completed | 15 | 15 | 11.5 | 11.3 | PLOT NO 13 | ROAD | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 13 | 13 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 14 | PLOT NO 12 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 14 | 14 | Residential | ODD SIZE | 130 | Stage 2 | Completed | 9 | 9 | 14.5 | 14.5 | PLOT NO 15 | PLOT NO 13 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 15 | 15 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 16 | PLOT NO 14 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 16 | 16 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 17 | PLOT NO 15 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 17 | 17 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 18 | PLOT NO 16 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 18 | 18 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 19 | PLOT NO 17 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 19 | 19 | Residential | ODD SIZE | 99 | Stage 2 | Completed | 15 | 15 | 6.7 | 6.5 | 3 MTR ROAD & C A SITE | PLOT NO 18 | SY NO 120/3B APPROVED LAYOUT | ROAD |
| 20 | 20 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 21 | SY NO 127 | ROAD | 3 MTR ROAD & PARK |
| 21 | 21 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 22 | PLOT NO 20 | ROAD | 3 MTR ROAD & PARK |
| 22 | 22 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 23 | PLOT NO 21 | ROAD | 3 MTR ROAD & PARK |
| 23 | 23 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 24 | PLOT NO 22 | ROAD | 3 MTR ROAD & PARK |
| 24 | 24 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 25 | PLOT NO 23 | ROAD | 3 MTR ROAD & PARK |
| 25 | 25 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 26 | PLOT NO 24 | ROAD | 3 MTR ROAD & PARK |
| 26 | 26 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 27 | PLOT NO 25 | ROAD | 3 MTR ROAD & PARK |
| 27 | 27 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 28 | PLOT NO 26 | ROAD | 3 MTR ROAD & PARK |
| 28 | 28 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 29 | PLOT NO 27 | ROAD | 3 MTR ROAD & PARK |
| 29 | 29 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 30 | PLOT NO 28 | ROAD | 3 MTR ROAD & PARK |
| 30 | 30 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 31 | PLOT NO 29 | ROAD | 3 MTR ROAD & PARK |
| 31 | 31 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 32 | PLOT NO 30 | ROAD | 3 MTR ROAD & PARK |
| 32 | 32 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 33 | PLOT NO 31 | ROAD | 3 MTR ROAD & PARK |
| 33 | 33 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 34 | PLOT NO 32 | ROAD | 3 MTR ROAD & PARK |
| 34 | 34 | Residential | 9*15 | 135 | Stage 2 | Completed | 9 | 9 | 15 | 15 | PLOT NO 35 | PLOT NO 33 | ROAD | 3 MTR ROAD & PARK |
| 35 | 35 | Residential | ODD SIZE | 189 | Stage 2 | Completed | 9 | 9 | 12.3 | 12.9 | ROAD | PLOT NO 34 | ROAD | 3 MTR ROAD & PARK |
| 36 | 36 | Residential | ODD SIZE | 128 | Stage 2 | Completed | 10.2 | 10.2 | 14 | 13.1 | PLOT NO 37 | ROAD | ROAD | 3 MTR ROAD & PARK |
| 37 | 37 | Residential | 12*ODD | 122.4 | Stage 2 | Completed | 10.2 | 10.2 | 12 | 12 | PLOT NO 38 | PLOT NO 36 | ROAD | 3 MTR ROAD & PARK |
| 38 | 38 | Residential | 12*ODD | 122.4 | Stage 2 | Completed | 10.2 | 10.2 | 12 | 12 | PLOT NO 39 | PLOT NO 37 | ROAD | 3 MTR ROAD & PARK |
| 39 | 39 | Residential | 12*ODD | 123 | Stage 2 | Completed | 10.2 | 10.2 | 12 | 12 | PLOT NO 40 | PLOT NO 38 | ROAD | 3 MTR ROAD & PARK |
| 40 | 40 | Residential | 12*ODD | 110 | Stage 2 | Completed | 1.5 | 10.3 | 12 | 12 | PLOT NO 41 | PLOT NO 39 | ROAD | 3 MTR ROAD & PARK |
| 41 | 41 | Residential | ODD SIZE | 94.5 | Stage 2 | Completed | 10.5 | 10.5 | 9 | 9 | 3 MTR ROAD & C A SITE | PLOT NO 40 | ROAD | 3 MTR ROAD & PARK |
| Sl No | Project Work | Is Applicable ? | Estimated From Date | Estimated To Date |
|---|---|---|---|---|
| 1 | Ground Clearance/Formation Of Plots | Yes | 01-07-2023 | 31-08-2023 |
| 2 | Formation Of Road, Footpath | Yes | 01-08-2023 | 30-09-2023 |
| 3 | Construction Of Water Supply Infrastucture | Yes | 01-09-2023 | 30-10-2023 |
| 4 | Construction Of Sewage System Infrastucture | Yes | 01-09-2023 | 30-10-2023 |
| 5 | Power Supply Work(Transformer & Substation) | Yes | 01-01-2024 | 31-01-2024 |
| 6 | Construction Of Storm Water Drainage | Yes | 01-09-2023 | 30-11-2023 |
| 7 | Solid Waste Management and Disposal | No | ||
| 8 | Tree Plantation And LandScape Work | Yes | 01-10-2023 | 31-12-2023 |
| 9 | Street Lighting | Yes | 01-02-2024 | 28-02-2024 |
| 10 | Sewage Treatment Plant (STP) | No | ||
| 11 | Other Miscellaneous Work | Yes | 01-07-2023 | 16-03-2024 |
| SlNo. | Work | Is Applicable ? |
|---|---|---|
| 1 | Electricity | Yes |
| 2 | Smart home automation | No |
| 3 | CCTV surveillance | No |
| 4 | Club House | No |
| 5 | Community Hall | No |
| 6 | Outdoor Sports facility | No |
| 7 | Indoor sports facility | No |
| 8 | Swimming Pools | No |
| 9 | Gym | No |
| 10 | Parks | Yes |
| 11 | Power Backup | No |
| 12 | Piped Gas | No |
| 13 | Water and Sanitation | Yes |
| 14 | Air conditioning | No |
| Total number of Plots | 41 |
| No. of Public and Semi Pubic Sites | 1 |
| Area of Public and Semi Pubic Sites(in Sq.m) | 571 |
| No. of Parks and Open Spaces | 2 |
| Area of Parks and Open Spaces(in Sq.m) | 1144 |
| Area of Road/Transportation(in Sq.m) | 3831 |
| Complaints on Promoter | No Complaints Found. |
| Complaints on Project | No Complaints Found. |


Ask Pulse Ai anything about real estate