New Launch - India Real Estate Report 2026.

Aakriti Esta E

AAKRITI CONSTRUCTIONS AND DEVELOPERS PRIVATE LIMITED

JUBILEE HILLS

RERA approved

Approved

10th Jul 2023

Completion pending

Pending

10th Jul 2028

Registration No.

P01100008198

Project Type

Residential

Approving Authority

HMDA

District

Hyderabad

Taluka

Shaikpet

State

Telangana

Project Details

Registration No.P01100008198
Certificate No.P01100008198
Project StatusOn-Going Project
Project TypeResidential
Authority NameHMDA
Plan Approval No.102436/BP/Plg/HMDA/2014
Proposed Completion2028-07-10
DistrictHyderabad
MandalShaikpet
StreetTellapur
LocalityJUBILEE HILLS
Pin Code500033
Last Modified2026-04-15

Land Details

Sy.No./TS No.96(P), 156(P), 157(P) and 158(P)
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)15680.08
Net Area (sqmts)15077.62
Total Building Units1
Approved Built-up Area8053.10
Boundaries EastNeighbors Land Sy No 97P and 154P
Boundaries WestNeighbors Land Sy No 96P 157P and 158P
Boundaries North12 feet wide proposed road
Boundaries SouthNeighbors Land Sy No 156 P

Parking

KOTHARI KUMAR MANOJManaging Director
KOTHARI KUMAR MANOJ_1Authorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation95
2X number of Basement(s) and Plinth50
3X number of Podiums40
4Stilt Floor20
5X number of Slabs of Super Structure15
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
11Overall Percentage of Completion of the work done For the entire Building /Wing22

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy