Aparna Aqua

APARNA INFRAHOUSING PRIVATE LIMITED

BANJARA HILLS

RERA approved

Approved

4th Oct 2022

Completion pending

Pending

31st Dec 2028

Registration No.

P02400006590

Project Type

Residential

Approving Authority

HMDA

District

Hyderabad

Taluka

Village/City/Town

State

Telangana

Project Details

Registration No.P02400006590
Certificate No.P02400006590
Project StatusNew Project
Project TypeResidential
Authority NameHMDA
Plan Approval No.004294/BP/HMDA/0791/SKP/2022
Proposed Completion2028-12-31
DistrictHyderabad
MandalVillage/City/Town
StreetRaidurga
LocalityBANJARA HILLS
Pin Code500034
Last Modified2026-04-14

Land Details

Sy.No./TS No.Sy No 11(P)of raidurga khalsa ,Sy No 17(P) of raidurga nav khalsa, Sy No80 and 81 of Manikonda Jagir
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)21188.3
Net Area (sqmts)21187.25
Total Building Units3
Approved Built-up Area197640.01
Mortgage Area31658.47
Boundaries EastNala and Sy No 82p
Boundaries WestLand in Sy No 246 of Manikonda jagir
Boundaries North30MT Wide Road
Boundaries SouthLand in Sy No 246 of Manikonda jagir

Parking

SUBRAMANYAM REDDY SANNAREDDYDirector
SUBRAMANYAM REDDY SANAREDDYAuthorized Signatory
VENKATESWARA REDDY CHENNURUDirector
VENKATESWARA REDDY CHENNURU_1Authorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor0
5X number of Slabs of Super Structure32
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises5
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.33
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor0
5X number of Slabs of Super Structure24
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises2
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor0
5X number of Slabs of Super Structure35
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises4
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.35
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy