APARNA KANOPY YELLOW BELLS

APARNA CONSTRUCTIONS AND ESTATES PVT LTD

BANJARA HILLS

RERA approved

Approved

23rd Feb 2021

Completion pending

Pending

23rd Feb 2027

Registration No.

P02200002940

Project Type

Residential

Approving Authority

HMDA

District

Hyderabad

Taluka

KHAIRTABAD

State

Telangana

Project Details

Registration No.P02200002940
Certificate No.P02200002940
Project StatusNew Project
Project TypeResidential
Authority NameHMDA
Plan Approval No.040124/MED/R1/U6/HMD
Proposed Completion2027-02-23
DistrictHyderabad
MandalKHAIRTABAD
StreetGundlapochampally
LocalityBANJARA HILLS
Pin Code500034
Last Modified2025-04-24

Land Details

Sy.No./TS No.452(P), 453(P),454,459(P),484(P),485(P) & 486
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)42697.97
Net Area (sqmts)42697.97
Total Building Units10
Approved Built-up Area150488.69
Mortgage Area19969.22
Boundaries EastExisting 33M Wide Road
Boundaries WestApparel Park and Land in Survey No 508
Boundaries NorthNeighbours Land and Survey Nos 487 and 489
Boundaries SouthAparna Kanopy Marigold

Parking

SANNAREDDY SUBRAMANYAM REDDYManaging Director
VENKATESWAR REDDY CHENNURUDirector
SANNAREDDY SUBRAMANYAM REDDY_1Authorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.100
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy