G SQUARE
DEFINATION REALITY LLP
BANJARA HILLS
Approved
19th Jul 2017
Completed
20th Feb 2020
Registration No.
P02400000777
Project Type
Commercial
Approving Authority
GHMC
District
Hyderabad
Taluka
Village/City/Town
State
Telangana
Project Details
| Registration No. | P02400000777 |
| Certificate No. | P02400000777 |
| Project Status | Completed |
| Project Type | Commercial |
| Authority Name | GHMC |
| Plan Approval No. | 53291/HO/WZ/Cir-11/2016 |
| Proposed Completion | 2020-02-20 |
| District | Hyderabad |
| Mandal | Village/City/Town |
| Street | OLD MUMBAI HIGHWAY |
| Locality | BANJARA HILLS |
| Pin Code | 500034 |
| Last Modified | 2019-05-20 |
Land Details
| Sy.No./TS No. | 79 |
| Plot No./House No. | Total Area(In sqmts) |
| Total Area (sqmts) | 4300 |
| Net Area (sqmts) | 3641.00 |
| Total Building Units | 1 |
| Approved Built-up Area | 15718.09 |
| Mortgage Area | 1605 |
| Boundaries East | RAI DURGAM POLICE STATION |
| Boundaries West | NEIGHBOURS LAND |
| Boundaries North | ROAD |
| Boundaries South | NEIGHBOURS LAND |
Parking
| ABHISH KUMAR | Authorized Signatory |
| ABHISH KUMAR_1 | Partner |
| MITHUN KHAITAN | Authorized Signatory |
| MITHUN KHAITAN_1 | Partner |
| PRASHANT SHRIMAL | Partner |
| RAJKUMAR KABRA | Partner |
Construction Progress
| Sr.No. | Task/Activity | % Completed |
|---|---|---|
| 1 | Excavation | 100 |
| 2 | X number of Basement(s) and Plinth | 100 |
| 3 | X number of Podiums | 0 |
| 4 | Stilt Floor | 0 |
| 5 | X number of Slabs of Super Structure | 65 |
| 6 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | 30 |
| 7 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | 0 |
| 8 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | 10 |
| 9 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | 5 |
| 10 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | 10 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in