Hivision Heights

Hivision Construction

Banjara Hills

RERA approved

Approved

27th Aug 2021

Completion pending

Pending

27th Aug 2027

Registration No.

P02200004429

Project Type

Residential

Approving Authority

HMDA

District

Hyderabad

Taluka

Shaikpet

State

Telangana

Project Details

Registration No.P02200004429
Certificate No.P02200004429
Project StatusNew Project
Project TypeResidential
Authority NameHMDA
Plan Approval No.024876/MED/R1/U6/HMD
Proposed Completion2027-08-27
DistrictHyderabad
MandalShaikpet
Streetcine planet Lane
LocalityBanjara Hills
Pin Code500081
Last Modified2025-06-14

Land Details

Sy.No./TS No.105/D
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)16313.50
Net Area (sqmts)16313.50
Total Building Units2
Approved Built-up Area63165.64
Mortgage Area6344.03
Boundaries EastGarden Society
Boundaries WestOpen Land
Boundaries North40 feet road
Boundaries SouthOpen Land

Parking

Sameer GilaniAuthorized Signatory
Sairoz HiraniAuthorized Signatory
Sadiq GilaniAuthorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure80
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises10
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.60
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises30
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.80
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy