NAYANS NATURE SPRINGS
NAYAN CONSTRUCTIONS
KUKATPALLY
Approved
20th Nov 2019
Completed
20th Nov 2025
Registration No.
P02200001561
Project Type
Residential
Approving Authority
GHMC
District
Hyderabad
Taluka
Village/City/Town
State
Telangana
Project Details
| Registration No. | P02200001561 |
| Certificate No. | P02200001561 |
| Project Status | Completed |
| Project Type | Residential |
| Authority Name | GHMC |
| Plan Approval No. | Project Name |
| Proposed Completion | 2025-11-20 |
| District | Hyderabad |
| Mandal | Village/City/Town |
| Street | KUKATPALLY |
| Locality | KUKATPALLY |
| Pin Code | 500072 |
| Last Modified | 2020-01-04 |
Land Details
| Sy.No./TS No. | 488, 489, 490 |
| Plot No./House No. | Total Area(In sqmts) |
| Total Area (sqmts) | 12433.69 |
| Net Area (sqmts) | 12433.69 |
| Total Building Units | 3 |
| Approved Built-up Area | 39061.68 |
| Mortgage Area | 4022.81 |
| Boundaries East | 40 FEET WIDE ROAD AND LAND IN SY NOS 485 486 487 |
| Boundaries West | LAND IN SURVEY NO 518 |
| Boundaries North | LAND IN SURVEY NO 490 PART |
| Boundaries South | LAND IN SURVEY NOS 519 AND 520 AND 487 |
Parking
| JEEVAN REDDY VATTI | Authorized Signatory |
| JEEVAN REDDY VATTI_1 | Partner |
| SUDARSHAN RAO KUENAIAHGARI | Partner |
| RAVINDER REDDY MEKALA | Partner |
| JOHN BOSCO REDDY THUMMA | Partner |
| SRIDHAR REDDY BASANI | Partner |
| SURESH KUMAR REDDY BASANI | Partner |
| AVINASH RAO NAINENI | Partner |
Construction Progress
| Sr.No. | Task/Activity | % Completed |
|---|---|---|
| 1 | Excavation | 20 |
| 2 | X number of Basement(s) and Plinth | 0 |
| 3 | X number of Podiums | 0 |
| 4 | Stilt Floor | 0 |
| 5 | X number of Slabs of Super Structure | 0 |
| 6 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | 0 |
| 7 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | 0 |
| 8 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | 0 |
| 9 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | 0 |
| 10 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | 0 |
| 1 | Excavation | 0 |
| 2 | X number of Basement(s) and Plinth | 0 |
| 3 | X number of Podiums | 0 |
| 4 | Stilt Floor | 0 |
| 5 | X number of Slabs of Super Structure | 0 |
| 6 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | 0 |
| 7 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | 0 |
| 8 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | 0 |
| 9 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | 0 |
| 10 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | 0 |
| 1 | Excavation | 0 |
| 2 | X number of Basement(s) and Plinth | 0 |
| 3 | X number of Podiums | 0 |
| 4 | Stilt Floor | 0 |
| 5 | X number of Slabs of Super Structure | 0 |
| 6 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | 0 |
| 7 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | 0 |
| 8 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | 0 |
| 9 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | 0 |
| 10 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | 0 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in