SHIVAMS TEJAS
SHIVAMS INFRA AND DEVELOPERS
GUNJ BAZAR
Approved
19th Feb 2019
Completed
19th Feb 2025
Registration No.
P02200000963
Project Type
Commercial
Approving Authority
GHMC
District
Hyderabad
Taluka
Village/City/Town
State
Telangana
Project Details
| Registration No. | P02200000963 |
| Certificate No. | P02200000963 |
| Project Status | Completed |
| Project Type | Commercial |
| Authority Name | GHMC |
| Plan Approval No. | Project Name |
| Proposed Completion | 2025-02-19 |
| District | Hyderabad |
| Mandal | Village/City/Town |
| Street | ZP ROAD |
| Locality | GUNJ BAZAR |
| Pin Code | 500003 |
| Last Modified | 2021-08-11 |
Land Details
| Sy.No./TS No. | 218/1/2 |
| Plot No./House No. | 186 AND 187 |
| Total Area (sqmts) | 1783.74 |
| Net Area (sqmts) | 1635.09 |
| Total Building Units | 1 |
| Approved Built-up Area | 5573.34 |
| Mortgage Area | 551.03 |
| Boundaries East | PLOT NO 185 |
| Boundaries West | PLOT NO 188 |
| Boundaries North | ROAD |
| Boundaries South | PLOT NO 191 92 193 AND 194 |
Parking
| GAUTAMCHAND JAIN | Authorized Signatory |
| KANCHAN DEVI | Partner |
| MEENA DEVI | Partner |
| INDERCHAND DEORA | Partner |
Construction Progress
| Sr.No. | Task/Activity | % Completed |
|---|---|---|
| 1 | Excavation | 100 |
| 2 | X number of Basement(s) and Plinth | 100 |
| 3 | X number of Podiums | 100 |
| 4 | Stilt Floor | 100 |
| 5 | X number of Slabs of Super Structure | 100 |
| 6 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | 100 |
| 7 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | 100 |
| 8 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | 100 |
| 9 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | 100 |
| 10 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | 100 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in