New Launch - India Real Estate Report 2026.

SRI ADITYA PEACHTREE - THE RESERVE

SRIADITYA HOMES PRIVATE LIMITED

BANJARA HILLS

RERA approved

Approved

24th Mar 2021

Completion pending

Pending

23rd Mar 2027

Registration No.

P02400003220

Project Type

Residential

Approving Authority

HMDA

District

Hyderabad

Taluka

KHAIRTABAD

State

Telangana

Project Details

Registration No.P02400003220
Certificate No.P02400003220
Project StatusNew Project
Project TypeResidential
Authority NameHMDA
Plan Approval No.000168/LO/PLG/HMDA/2
Proposed Completion2027-03-23
DistrictHyderabad
MandalKHAIRTABAD
StreetSURVEY NO. 142
LocalityBANJARA HILLS
Pin Code500034
Last Modified2026-01-15

Land Details

Sy.No./TS No.142
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)67570.13
Net Area (sqmts)67570.13
Total Building Units39
Approved Built-up Area30100.33
Mortgage Area1505
Boundaries EastLAND IN SURVEY NO 141
Boundaries WestLAND IN SURVEY NO 153 OF SRI KRISHNA GOSEVA MANDAL
Boundaries NorthLAND IN SY NO 153 AND 143 AND 40 FT APPROACH ROAD
Boundaries SouthLAND IN SURVEY NO 396 OF MANCHIREVULA VILLAGE

Parking

V KOTA REDDYManaging Director
V SUPRAJADirector
V ADITYA REDDYAuthorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing80
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises65
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing99
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate85
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises50
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate95
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate60
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises93
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises78
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises85
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises85
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises87
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate80
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises100
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises100
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing100
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises95
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises90
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing95
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises90
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises80
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing90
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate100
1Excavation100
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises80
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate50

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy