New Launch - India Real Estate Report 2026.

THE FIRST

DSR BUILDERS AND DEVELOPERS

MADHAPUR

RERA approved

Approved

9th May 2017

Project completed

Completed

8th May 2023

Registration No.

P02400000469

Project Type

Mixed Development (Residential & Commercial)

Approving Authority

GHMC

District

Hyderabad

Taluka

Village/City/Town

State

Telangana

Project Details

Registration No.P02400000469
Certificate No.P02400000469
Project StatusCompleted
Project TypeMixed Development (Residential & Commercial)
Authority NameGHMC
Plan Approval No.Project Name
Proposed Completion2023-05-08
DistrictHyderabad
MandalVillage/City/Town
StreetPAN MAKTHA VILLAGE
LocalityMADHAPUR
Pin Code500081
Last Modified2020-09-07

Land Details

Sy.No./TS No.66/2
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)15302.80
Net Area (sqmts)14669.26
Total Building Units2
Approved Built-up Area114785.45
Mortgage Area11645.73
Boundaries EastPART OF SURVEY NO 66-2
Boundaries WestPART OF SURVEY NO 66-2
Boundaries NorthMAIN ROAD
Boundaries SouthLAND OF ROAD MYSTRY COLLEGE

Parking

SOBHA DEVIREDDYPartner
ABHISHEK DEVIREDDYPartner
SWETHA DEVIREDDYPartner
ABHIVARSHINI PUCHALAPALLIPartner
RAGHURAMI REDDY DEVIREDDYPartner
RAGHURAMI REDDY DEVIREDDY_1Authorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums50
4Stilt Floor55
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises65
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises20
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.20
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing25
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate5
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums80
4Stilt Floor80
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.20
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy