Project Details

Registration No.P02200000868
Certificate No.P02200000868
Project StatusCompleted
Project TypeResidential
Authority NameGHMC
Plan Approval No.53078/HO/EZ/Cir-1/2016
Proposed Completion2020-02-15
DistrictMedchal-Malkajgiri
MandalKapra
StreetKANDIGUDA
LocalityKANDHIGUDA
Pin Code500094
Last Modified2019-06-03

Land Details

Sy.No./TS No.606, 608/1 AND 609 PART
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)13589.97
Net Area (sqmts)13230.78
Total Building Units4
Approved Built-up Area13589.97
Mortgage Area1396.13
Boundaries EastMUNICIPAL PARK OF KANDIGUDA VILLAGE
Boundaries WestAMMUGUDA VILLAGE
Boundaries North60 WIDE ROAD
Boundaries SouthHOUSES OF KANDIGUDA VILLAGE

Parking

POLISETTY BABU RAOManaging Director
POLISETYT RAVI KUMARAuthorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor100
5X number of Slabs of Super Structure7
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor100
5X number of Slabs of Super Structure0
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor100
5X number of Slabs of Super Structure7
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums0
4Stilt Floor100
5X number of Slabs of Super Structure7
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing50
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Warangal

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy