NAVYA PINNACLE
S S CONSTRUCTIONS
MOULALI
Approved
5th Jul 2024
Pending
5th Jul 2027
Registration No.
P02200008598
Project Type
Residential
Approving Authority
GHMC
District
Ranga Reddy
Taluka
Village/City/Town
State
Telangana
Project Details
| Registration No. | P02200008598 |
| Certificate No. | P02200008598 |
| Project Status | New Project |
| Project Type | Residential |
| Authority Name | GHMC |
| Plan Approval No. | 113456789 |
| Proposed Completion | 2027-07-05 |
| District | Ranga Reddy |
| Mandal | Village/City/Town |
| Street | UPPAL |
| Locality | MOULALI |
| Pin Code | 500040 |
| Last Modified | 2026-05-18 |
Land Details
| Sy.No./TS No. | 1 TO 40, 282 TO 368, 369(P), 370 TO 373, 374(P), 375 TO 387, 395 TO 401, 454, 456 TO 459, 505(P), 510 TO 564 |
| Plot No./House No. | 1393 PART |
| Total Area (sqmts) | 745.69 |
| Net Area (sqmts) | 745.69 |
| Total Building Units | 1 |
| Approved Built-up Area | 1915.60 |
| Boundaries East | PART OF PLOT NO 1393 |
| Boundaries West | PLOT NO-1394 |
| Boundaries North | PLOT NO-1390 |
| Boundaries South | 80 FEET WIDE ROAD |
Parking
| MADHU YARABARLA | Authorized Signatory |
| MADHU YARABARLA_1 | Proprietor |
Construction Progress
| Sr.No. | Task/Activity | % Completed |
|---|---|---|
| 1 | Excavation | 100 |
| 2 | X number of Basement(s) and Plinth | 100 |
| 3 | X number of Podiums | 0 |
| 4 | Stilt Floor | 100 |
| 5 | X number of Slabs of Super Structure | 100 |
| 6 | Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises | 80 |
| 7 | Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises | 0 |
| 8 | Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks. | 70 |
| 9 | The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing | 50 |
| 10 | Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate | 0 |
| 11 | Overall Percentage of Completion of the work done For the entire Building /Wing | 60 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in