Ramky One Symphony

RAMKY ESTATES AND FARMS LTD

P JANARDHAN REDDY NAGAR

RERA approved

Approved

4th Jun 2021

Completion pending

Pending

4th Jun 2027

Registration No.

P01100003145

Project Type

Residential

Approving Authority

GHMC

District

Ranga Reddy

Taluka

Serilingampally

State

Telangana

Project Details

Registration No.P01100003145
Certificate No.P01100003145
Project StatusNew Project
Project TypeResidential
Authority NameGHMC
Plan Approval No.1/C22/07250/2021
Proposed Completion2027-06-04
DistrictRanga Reddy
MandalSerilingampally
StreetMumbai Highway
LocalityP JANARDHAN REDDY NAGAR
Pin Code500032
Last Modified2025-01-18

Land Details

Sy.No./TS No.843/P & 844/P
Plot No./House No.843/P & 844/P
Total Area (sqmts)56042.40
Net Area (sqmts)56042.40
Total Building Units10
Approved Built-up Area180306.52
Mortgage Area18563.64
Boundaries EastNeighbours land
Boundaries WestNALA
Boundaries NorthNational Highway and ORR Service road
Boundaries SouthNeighbours land

Parking

NANDA KISHORE MUDUMBAIManaging Director
SHARAN ALLAAuthorized Signatory

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises75
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises45
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.25
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing35
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate7
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises50
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.30
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing25
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.55
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises60
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises40
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.55
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing60
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate20
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor0
5X number of Slabs of Super Structure0
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor80
5X number of Slabs of Super Structure75
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises2
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor80
5X number of Slabs of Super Structure45
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth50
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure0
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation5
2X number of Basement(s) and Plinth0
3X number of Podiums0
4Stilt Floor0
5X number of Slabs of Super Structure0
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises0
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0
1Excavation100
2X number of Basement(s) and Plinth100
3X number of Podiums100
4Stilt Floor100
5X number of Slabs of Super Structure95
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises10
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises0
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.0
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing0
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate0

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy