Project Details

Registration No.P02200000908
Certificate No.P02200000908
Project StatusCompleted
Project TypeResidential
Authority NameHMDA
Plan Approval No.Project Name
Proposed Completion2024-10-31
DistrictRanga Reddy
MandalSaroornagar
StreetSy.No.102 Om Vihar Colony, Medipally, Hyderabad-500039
LocalityCHAITANYAPURI
Pin Code500060
Last Modified2019-05-31

Land Details

Sy.No./TS No.102 PART
Plot No./House No.10-132
Total Area (sqmts)2077.61
Net Area (sqmts)2077.61
Total Building Units40
Approved Built-up Area5156.1
Mortgage Area577.16
Boundaries EastSY NO 102 PART
Boundaries WestSY NO 102 PART
Boundaries North30 FEET ROAD
Boundaries SouthSY NO 101 PART

Parking

ANJAN REDDY SINGIREDDYAuthorized Signatory
BHASKAR KARNATIPartner
SRIDHAR ADDAGATLAPartner
NAVEEN KARNATIPartner

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00
1Excavation00
2X number of Basement(s) and Plinth00
3X number of Podiums00
4Stilt Floor00
5X number of Slabs of Super Structure00
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises00
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises00
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.00
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing00
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate00

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Warangal

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy