VEDANT

WISE EARTH CONSTRUCTIONS LLP

NARSINGHI

RERA approved

Approved

10th Dec 2021

Completion pending

Pending

10th Dec 2027

Registration No.

P02400004176

Project Type

Residential

Approving Authority

HMDA

District

Ranga Reddy

Taluka

Gandipet

State

Telangana

Project Details

Registration No.P02400004176
Certificate No.P02400004176
Project StatusNew Project
Project TypeResidential
Authority NameHMDA
Plan Approval No.Project Name
Proposed Completion2027-12-10
DistrictRanga Reddy
MandalGandipet
StreetJAI HIND RESIDENCY LAYOUT
LocalityNARSINGHI
Pin Code500089
Last Modified2026-05-08

Land Details

Sy.No./TS No.Plot No./House No.
Plot No./House No.Total Area(In sqmts)
Total Area (sqmts)22810.25
Net Area (sqmts)14231.59
Total Building Units4
Approved Built-up Area75584.35
Mortgage Area10458.68
Boundaries EastSY NO 37 39
Boundaries WestSY NO 35 31
Boundaries NorthGOVERNMENT LAND
Boundaries SouthSY NO 54 55 56

Parking

AJAY CHANDRA DEVPartner
AJAY CHANDRA DEV_1Authorized Signatory
TRIPURANENI HARI KRISHNAPartner

Construction Progress

Sr.No.Task/Activity% Completed
1Excavation100
2X number of Basement(s) and Plinth99
3X number of Podiums0
4Stilt Floor98
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises70
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate65
1Excavation100
2X number of Basement(s) and Plinth99
3X number of Podiums0
4Stilt Floor98
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises70
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate65
1Excavation100
2X number of Basement(s) and Plinth99
3X number of Podiums0
4Stilt Floor98
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises70
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate65
1Excavation100
2X number of Basement(s) and Plinth99
3X number of Podiums0
4Stilt Floor98
5X number of Slabs of Super Structure100
6Internal walls, Internal Plaster, Floorings within Flats/Premises, Doors and Windows to each of the Flat/Premises70
7Sanitary Fittings within the Flat/Premises,Electrical Fittings within the Flat/Premises70
8Staircases, Lifts Wells and Lobbies at each Floor level connecting Staircases and Lifts, Overhead and Underground Water Tanks.90
9The external plumbing and external plaster, elevation, completion of terraces with waterproofing of the Building/Wing85
10Installation of lifts, water pumps, Fire Fighting Fittings and Equipment as per CFO NOC, Electrical fittings to Common Areas, electro, mechanical equipment, Compliance to conditions of environment /CRZ NOC, Finishing to entrance lobby/s, plinth protection, paving of areas appurtenant to Building/Wing, Compound Wall and all other requirements as may be required to Obtain Occupation /Completion Certificate65

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Hyderabad

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy