PARADISE HEIGHTS
GANGA VIDHYA PROPERTY HUB PRIVATE LIMITED
Etah, Uttar Pradesh
Approved
1st Apr 2020
Completed
30th Sept 2022
Registration No.
UPRERAPRJ718120
Project Type
Residential
District
Etah
Taluka
Etah
State
Uttar Pradesh
Project Details
| RERA ID | UPRERAPRJ718120 |
| Project Status | Completed |
| Project Category | Residential |
| District | Etah |
| Taluka | Etah |
| Start Date | 2020-04-01 |
| Completion Date | 2022-09-30 |
| Total Area (sqm) | 522 |
| Project Cost (Lacs) | 298 |
| Duration (Months) | 30 |
| Registration Fee | 5220 |
Promoter Details
| Promoter Name | GANGA VIDHYA PROPERTY HUB PRIVATE LIMITED |
| Promoter ID | UPRERAPRM107596 |
| Mobile | 99******** |
Project Team
| role | name |
|---|---|
| Architect | Ashwani Shiromany |
| Contractor | M/s Pravesh Kumari |
| Structural Engineer | Devki Nandan Singh |
Land Details
| type | khasra_or_plot_no | area_sqmt |
|---|---|---|
| Plot | 117,Aruna Nagar | 260.86 |
| Plot | 117,Aruna Nagar | 260.86 |
Unit Configuration
| Block No | Floor Number | Flat/ Apartment/ Shop/Plot type | Number of Apartment/Flats/Shop | Unit Carpet Area (in sqm) | Open Parking Space (in Nos.) |
|---|---|---|---|---|---|
| PARADISE HEIGHTS | BSMNT | OTHER | 0 | 0 | - |
| PARADISE HEIGHTS | BSMNT2 | OTHER | 0 | 0 | - |
| PARADISE HEIGHTS | BSMNT3 | OTHER | 0 | 0 | - |
| PARADISE HEIGHTS | GF | OTHER | 0 | 0 | 0 |
| PARADISE HEIGHTS | 1 | 4 BHK | 1 | 95 | - |
| PARADISE HEIGHTS | 1 | 4 BHK | 1 | 94 | - |
| PARADISE HEIGHTS | 2 | 2 BHK | 2 | 41 | - |
| PARADISE HEIGHTS | 2 | 2 BHK | 1 | 39 | - |
| PARADISE HEIGHTS | 2 | 2 BHK | 1 | 38 | - |
| PARADISE HEIGHTS | 3 | 2 BHK | 2 | 41 | - |
| PARADISE HEIGHTS | 3 | 2 BHK | 1 | 39 | - |
| PARADISE HEIGHTS | 3 | 2 BHK | 1 | 38 | - |
Development Works
| work_name | description |
|---|---|
| Demarcation of Plots | The Project plot is clearly demarcated on site as per the sanctioned map. The Back and Front Set backs of 6 m are observed at site . |
| Boundary Wall | 8 to 10 feet high boundary wall, constructed with Brick- Mortar. Plaster and Painted. Designed to Resist Earthquake. |
| Road Work | Cement concrete pavement in the project compound , to provide anti skid surface for vehicle Movement |
| Footpaths | Not Applicable |
| Water Supply Including Drinking Water Facilities | Ground water is pumped to common tank through a pumping unit. Potable water will then be delivered to Kitchen Water and Wet areas of all residential flats through elegant and efficient plumbing system. |
| Sewer System | The project and all its units are connected through soil pipes, and a sewer line with convinient check units and controlled discharge. The sewer line is attached to sewer tank, thereon connected to the local authorities sewer drain for disposal |
| Drain | Storm water drain shall be Provided. Storm water from Roof paved areas shall be connected to the Storm water drain channel and then go to the Rain water harvesting Pit to recharge the Ground water and overflow will be connected with local authority drain |
| Parks | Not Applicable |
| Tree Planting | Trees will be planted near Boundary walls |
| Design For Electric Supply Including Street Lighting | Electrical design is done to cater for the domestic usage of the project flats along with common faiclities, as per electrical department rules. The project also intend to provide 24x7 electricity back up. |
| Community Buildings | Not Applicable |
| Treatment and Disposal System of Sewage and Sullage water | Not Applicable |
| Solid Waste Management And Disposal System | Solid waste collection units will be placed at suitable location on every floor, and a common collection point in the project for ease of disposal through local body collection trucks |
| Water Conservation System | We will use low flow fixtures and rain water harvesting system to reduce the water consumption and improve the ground water level. |
| Energy Management System Including Use of Renewable Energy | Not Applicable |
| Fire Protection And Fire Safety System | A state of Art fire protection system will be installed, where a water tank is installed as per Fire department Norms , a strong sturdy plumbing arrangement to cater fire will be installed across all the common areas of project. |
| Social Infrastructure And Other Public Amenities Including Public Health Services | Not Applicable |
| Emergency Evacuation Services | Wide Stairs to assist easy evacuation. Also confirming to the Norms of Fire Department. |
| Other Miscellaneous Work | As per Project Requirement |
Bank Details
| Bank Name | Bank of India |
| Branch | Etah |
| Branch Address | Post office road, Civil Lines Etah |
| Account Holder | Ganga Vidhya Property Hub Pvt. Ltd. |
| Account Number | 726020110000234 |
| IFSC Code | BKID0007260 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in