New Launch - India Real Estate Report 2026.

Jaypee Greens Pavilion Heights Arcade, Noida

Jaiprakash Associates Limited

Gautam Buddha Nagar, Uttar Pradesh

RERA approved

Approved

26th Oct 2016

Project completed

Completed

30th Apr 2018

Registration No.

UPRERAPRJ3904

Project Type

Commercial

District

Gautam Buddha Nagar

Taluka

Gautam Buddha Nagar

State

Uttar Pradesh

Project Details

RERA IDUPRERAPRJ3904
Project StatusCompleted
Project CategoryCommercial
DistrictGautam Buddha Nagar
TalukaGautam Buddha Nagar
Start Date2016-10-26
Completion Date2018-04-30
Total Area (sqm)89
Project Cost (Lacs)0
Duration (Months)19
Registration Fee1780

Promoter Details

Promoter NameJaiprakash Associates Limited
Promoter IDUPRERAPRM6273
Mobile96********

Project Team

rolename
Architect"M/s ARCOP ASSOCIATES PVT. LTD"
ContractorJaiprakash Associates Limited
Structural EngineerM/s VINTECH

Land Details

typekhasra_or_plot_noarea_sqmt
PlotC2-B5 - PART OF POCKET B-489

Unit Configuration

Block NoFloor NumberFlat/ Apartment/ Shop/Plot typeNumber of Apartment/Flats/ShopUnit Carpet Area (in sqm)Open Parking Space (in Nos.)
C2B5GFSHOP111.820
C2B5GFSHOP17.440
C2B5GFSHOP716.570
C2B5BSMNTOTHER00-

Development Works

work_namedescription
Demarcation of Plots"As per location of Plot : NE - Group Housing SE - Approach Road SW - 24 M wide Master Plan Road NW - Group Housing The Plot has been demarcated"
Boundary Wall"This Project is part of Wish Town Township. The over all boundary wall of Town Township has been constructed except few Passages. The Pavilion Heights Arcade is part of cluster planning designed for B-4 residential Group Housing. This development is mix of residential towers and convenient shopping. It is integrated and interlinked with way of landscaping, internal roads, jogging and cycling track, pathways etc. The Pavilion Heights Arcade has been constructed on its respective identified plot with boundary wall on three sides. "
Road Work"External and internal roads work of the project is completed. "
FootpathsThe pedestrian footpaths with Kerb Stone as per Landscape Plan have been completed at Township level. The foot paths for Pavilion Heights Arcade are complete.
Water Supply Including Drinking Water Facilities"The pipe lines for water supply have been laid and completed at Township Level. The drinking water is being supplied through water centres after necessary treatments. The required water supply connection has been provided. "
Sewer System"The pipe lines for Sewer System have been laid and completed at Township Level. The Sewage is being treated at Sewerage Treatment Plant. The required sewer system connection has been provided. "
Drain"The drainage system has been laid and completed at Township Level. The drainage water is being collected in lakes of Golf Courses. The required drainage connection has been provided. "
Parks"Parks / Play fields are planned at Township Level and are not applicable at convenient shopping level. "
Tree Planting"Tree planting as per approved landscape plan at township level is complete. The tree planting work is complete for Pavilion Heights Arcade. "
Design For Electric Supply Including Street Lighting"The electric supply from Grid Sub Station as planned for Wish Town is complete. The required electrical connection has been provided. "
Community BuildingsNot Applicable
Treatment and Disposal System of Sewage and Sullage water"The sewage will be treated at Sewerage Treatment Plant. The sullage will be converted into compost. The sullage water after necessary treatment will be supplied for flushing, irrigation and landscaping. "
Solid Waste Management And Disposal System"The solid waste collected from Imperial Arcade shops will be transferred to segregation centres planned / constructed at Sewerage Treatment Plant at Township level. The segregated waste is being transported through facility management maintenance company to the identified sites of Noida Authority for necessary disposal."
Water Conservation SystemTreated water from Sewerage Treatment Plant is being used for irrigation and flushing.
Energy Management System Including Use of Renewable EnergyAs per approved environment impact assessment authority advice
Fire Protection And Fire Safety SystemThe Fire Station with all the infrastructure facilities and staff has been provided at Township level. The Pavilion Heights Arcade has been provided with all the provisions of Fire Protection & Safety System as laid down in respective fire approval from the fire department.
Social Infrastructure And Other Public Amenities Including Public Health ServicesAt township level, 500 hundred Bed Super Speciality Hospital, Jaypee Institute of Information & Technology, Jaypee Public School, Temples, Convenient Shopping facilities, Club facilities etc. have already been provided
Emergency Evacuation ServicesPavilion Heights Arcade is single storey structure hence fire staicase is not required for such low height development.
Other Miscellaneous WorkAt Township Level Sewerage Treatment Plant & Service Centres, Electric Sub station with DG Power Backup, Fire Station, Parks & Playgrounds have been provided.

Bank Details

Bank NameICICI Bank
BranchExpress Trade Tower2
Branch AddressPlot No. B-36, Sec 132, Noida – 201303
Account HolderJaiprakash Associates Limited-CPHA
Account Number157905001271
IFSC CodeICIC0001579

The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in

Top Properties in Varanasi

Pexo Icon

Ask Pulse Ai anything about real estate

Unlock the Latest in Real Estate

News, Infographics, Blogs & More! Delivered to your inbox.

Proptech Pulse Logo

Data that drives action.
Insight that inspires action.
Technology that empowers action.“

Made with Love

Statue

© PropTech Pulse 2026, All rights reserved.

Terms of Use and Privacy Policy