CONSTRUCTION OF 192 HOUSES AT POCKET-D INDRAPRASTH YOJANA LONI GHAZIABAD
Ghaziabad Development Authority
Ghaziabad, Uttar Pradesh
Approved
16th Aug 2018
Completed
14th Aug 2021
Registration No.
UPRERAPRJ440273
Project Type
Residential
District
Ghaziabad
Taluka
Ghaziabad
State
Uttar Pradesh
Project Details
| RERA ID | UPRERAPRJ440273 |
| Project Status | Completed |
| Project Category | Residential |
| District | Ghaziabad |
| Taluka | Ghaziabad |
| Start Date | 2018-08-16 |
| Completion Date | 2021-08-14 |
| Total Area (sqm) | 4352 |
| Project Cost (Lacs) | 2563 |
| Duration (Months) | 36 |
| Registration Fee | 27000 |
Promoter Details
| Promoter Name | Ghaziabad Development Authority |
| Promoter ID | UPRERAPRM11404 |
| Mobile | 99******** |
Project Team
| role | name |
|---|---|
| Architect | Ms. Gyan P Mathur |
| Contractor | Ms. S.S. Construction Company |
| Structural Engineer | Mrs. Abha Gupta |
Land Details
| type | khasra_or_plot_no | area_sqmt |
|---|---|---|
| Khasra | 490 | 0.8507 |
Unit Configuration
| Block No | Floor Number | Flat/ Apartment/ Shop/Plot type | Number of Apartment/Flats/Shop | Unit Carpet Area (in sqm) | Open Parking Space (in Nos.) |
|---|---|---|---|---|---|
| tower D | 1 | 1 BHK | 2 | 36.50 | - |
| tower D | 2 | 1 BHK | 2 | 36.50 | - |
| tower D | 3 | 1 BHK | 2 | 36.50 | - |
| tower D | 4 | 1 BHK | 2 | 36.50 | - |
| tower D | 5 | 1 BHK | 2 | 36.50 | - |
| tower D | 6 | 1 BHK | 2 | 36.50 | - |
| tower D | 7 | 1 BHK | 2 | 36.50 | - |
| tower D | 8 | 1 BHK | 2 | 36.50 | - |
| tower D | 9 | 1 BHK | 2 | 36.50 | - |
| tower D | 10 | 1 BHK | 2 | 36.50 | - |
| tower D | 11 | 1 BHK | 2 | 36.50 | - |
| tower D | 12 | 1 BHK | 2 | 36.50 | - |
| tower D (2 BHK, Type-1) | 1 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 2 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 3 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 4 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 5 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 6 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 7 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 8 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 9 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 10 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 11 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-1) | 12 | 2 BHK | 4 | 47.75 | - |
| tower D (2 BHK, Type-2) | 1 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 2 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 3 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 4 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 5 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 6 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 7 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 8 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 9 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 10 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 11 | 2 BHK | 2 | 49.50 | - |
| tower D (2 BHK, Type-2) | 12 | 2 BHK | 2 | 49.50 | - |
| tower E | 1 | 1 BHK | 2 | 36.50 | - |
| tower E | 2 | 1 BHK | 2 | 36.50 | - |
| tower E | 3 | 1 BHK | 2 | 36.50 | - |
| tower E | 4 | 1 BHK | 2 | 36.50 | - |
| tower E | 5 | 1 BHK | 2 | 36.50 | - |
| tower E | 6 | 1 BHK | 2 | 36.50 | - |
| tower E | 7 | 1 BHK | 2 | 36.50 | - |
| tower E | 8 | 1 BHK | 2 | 36.50 | - |
| tower E | 9 | 1 BHK | 2 | 36.50 | - |
| tower E | 10 | 1 BHK | 2 | 36.50 | - |
| tower E | 11 | 1 BHK | 2 | 36.50 | - |
| tower E | 12 | 1 BHK | 2 | 36.50 | - |
| tower E (2 BHK, type-1) | 1 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 2 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 3 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 4 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 5 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 6 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 7 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 8 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 9 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 10 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 11 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-1) | 12 | 2 BHK | 4 | 47.75 | - |
| tower E (2 BHK, type-2) | 1 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 2 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 3 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 4 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 5 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 6 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 7 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 8 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 9 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 10 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 11 | 2 BHK | 2 | 49.50 | - |
| tower E (2 BHK, type-2) | 12 | 2 BHK | 2 | 49.50 | - |
Development Works
| work_name | description |
|---|---|
| Demarcation of Plots | East-Group housing plots, West- Block-C of Indraprastha Scheme, North- 18m wide road, South- Park and UGR |
| Boundary Wall | Boundary wall had been constructed on all outer sides of building with column and brick work and plaster has been done. |
| Road Work | Main Approach road mohan nagar to loni already exist. 18m wide road has constructed on north side of buildings. Cement Concrete road is constructed in front of houses with M-25 grade cement concrete |
| Footpaths | 1.5 m wide Footpath has been made with interlocking tiles. |
| Water Supply Including Drinking Water Facilities | Underground UGR has been constructed for drinking water and 110 mm dia PVC pipe line from UGR is connected to 80mm PVC pipe line which provide the water to the flats. |
| Sewer System | Providing and laying 300 mm NP-2 RCC hume pipe for sewer disposal connected with the existing main sewer line. |
| Drain | Surface drain is constructed both sides of the cement concrete road and it will be covered with pre-cast perforated RCC cover block. |
| Parks | providing and fixing of curve stone surrounding of the park |
| Tree Planting | tree planting will be provide |
| Design For Electric Supply Including Street Lighting | electricity transformers has been installed and street light will install all around the proposed building |
| Community Buildings | it is not proposed in the scheme. |
| Treatment and Disposal System of Sewage and Sullage water | Disposal System of Sewage and Sullage water by existing sewer line. |
| Solid Waste Management And Disposal System | it is not proposed in the scheme. |
| Water Conservation System | water conservation system will be provided with rain water harvesting system after completion of the building work |
| Energy Management System Including Use of Renewable Energy | Through power backup |
| Fire Protection And Fire Safety System | Fire Protection And Fire Safety System will be installed |
| Social Infrastructure And Other Public Amenities Including Public Health Services | Social Infrastructure And Other Public Amenities Including Public Health Services is nearby the scheme. |
| Emergency Evacuation Services | Emergency Evacuation Services is proposed in all side of buildings |
| Other Miscellaneous Work | Retro reflective signage board will be provided at the main gates |
Bank Details
| Bank Name | vijaya bank |
| Branch | Navyug market |
| Branch Address | Navyug market, ghaziabad |
| Account Holder | VC GDA ESCROW ACCOUNT SAMA |
| Account Number | 711301012000271 |
| IFSC Code | VIJB0007113 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in