Project Details
| RERA ID | UPRERAPRJ9518 |
| Project Status | Completed |
| Project Category | Residential |
| District | Gorakhpur |
| Taluka | Gorakhpur |
| Start Date | 2017-04-07 |
| Completion Date | 2022-05-30 |
| Total Area (sqm) | 15640 |
| Project Cost (Lacs) | 1253 |
| Duration (Months) | 62 |
| Registration Fee | 83500 |
Promoter Details
| Promoter Name | Gorakhpur Development Authority |
| Promoter ID | UPRERAPRM14553 |
| Mobile | 96******** |
Project Team
| role | name |
|---|---|
| Architect | V DESIGN ( ARCH. ANUPAM AGGRAWAL) |
| Contractor | VIRENDRA PRATAP SHUKLA |
| Structural Engineer | NEERAJ & ASSOCIATES |
Unit Configuration
| Block No | Floor Number | Flat/ Apartment/ Shop/Plot type | Number of Apartment/Flats/Shop | Unit Carpet Area (in sqm) | Open Parking Space (in Nos.) |
|---|---|---|---|---|---|
| 1 | GF | OTHER | 2 | 17.23 | 0 |
| 1 | GF | OTHER | 2 | 18.14 | 0 |
| 1 | 1 | 3 BHK | 4 | 75.16 | - |
| 1 | 3 | 3 BHK | 4 | 75.16 | - |
| 2 | GF | OTHER | 2 | 17.23 | 0 |
| 2 | GF | OTHER | 2 | 18.14 | 0 |
| 2 | 1 | 3 BHK | 4 | 75.16 | - |
| 2 | 2 | 3 BHK | 4 | 75.16 | - |
| 2 | 3 | 3 BHK | 4 | 75.16 | - |
| 3 | GF | OTHER | 2 | 17.23 | 0 |
| 3 | GF | OTHER | 2 | 18.14 | 0 |
| 3 | 1 | 3 BHK | 4 | 75.16 | - |
| 3 | 2 | 3 BHK | 4 | 75.16 | - |
| 3 | 3 | 3 BHK | 4 | 75.16 | - |
Development Works
| work_name | description |
|---|---|
| Demarcation of Plots | Blocks have been demarcated at site and work is in progress |
| Boundary Wall | boundary wall has been constructed at site |
| Road Work | Bituminous roads has been proposed. Trunk roads construction work is in progress. Link roads will be constructed after the construction of blocks |
| Footpaths | footpaths have been provisioned and shall be constructed after the construction of blocks |
| Water Supply Including Drinking Water Facilities | Trunk water supply lines for feeding these blocks are being laid. |
| Sewer System | Trunk lines are being laid at site. sewer lines will be laid at the end of construction of blocks |
| Drain | R.C.C. Trunk drains construction work is going on at site. Once the construction of blocks is over these lines shall be connected to the system |
| Parks | n/a |
| Tree Planting | Plantation shall be taken up after the construction of blocks and development of site |
| Design For Electric Supply Including Street Lighting | Electrical load as per UPPCL shall be sanctioned, installed, and shall be handed over to UPPCL for maintenance |
| Community Buildings | N/A |
| Treatment and Disposal System of Sewage and Sullage water | Primary treatment at block level through STP, secondary treatment proposed at STP |
| Solid Waste Management And Disposal System | garbage collection centre proposed at site |
| Water Conservation System | N/A |
| Energy Management System Including Use of Renewable Energy | N/A |
| Fire Protection And Fire Safety System | N/A |
| Social Infrastructure And Other Public Amenities Including Public Health Services | N/A |
| Emergency Evacuation Services | N/A |
| Other Miscellaneous Work | N/A |
Bank Details
| Bank Name | ANDHRA BANK |
| Branch | TARAMANDAL |
| Branch Address | TARAMANDAL, GORAKHPUR |
| Account Holder | SECRETARY, GDA, GORAKHPUR |
| Account Number | 153210100089563 |
| IFSC Code | ANDB0001532 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in
Top Properties in Lucknow


Ask Pulse Ai anything about real estate