| RERA ID | UPRERAPRJ981654/12/2024 |
| Project Status | New |
| Project Category | Mixed |
| District | Gorakhpur |
| Taluka | Gorakhpur |
| Start Date | 2024-08-13 |
| Completion Date | 2029-08-13 |
| Total Area (sqm) | 837730 |
| Project Cost (Lacs) | 70335 |
| Duration (Months) | 61 |
| Registration Fee | 6291000 |
Promoter Details
| Promoter Name | Gorakhpur Development Authority |
| Promoter ID | UPRERAPRM14553 |
| Mobile | 96******** |
Project Team
| role | name |
|---|---|
| Architect | ARPIT MODI |
| Contractor | MS GARUDA CONSTRUCTIONS AND ENGINEERING PVT LTD |
| Structural Engineer | NEERAJ GAUTAM |
Land Details
| type | khasra_or_plot_no | area_sqmt |
|---|---|---|
| Khasra | VILL HAMIDPUR 1, 2, 3, 4, 5,6,7,25/1,25/2,26,44,45,46,48,50mi, 52,53,54,55,56,58,62 | 71380 |
| Khasra | Village Fhatteypur Khasra No. 1,2,3, 4mi, 6mi, 7mi, 8mi, 11mi, 12mi, 13mi, 15mi, 16mi,17mi,18mi,21mi,22,23,24,32,35,36mi,37mi,38mi,84mi,85,90,91,92,93,94mi,98mi,99,100,101mi, 108mi, 111mi, 112mi, 118mi, 119mi, 121mi, 123,125mi | 257940 |
| Khasra | Village Salempur urf mugalpur Khasra No. 10,11,12,13,14,16mi,17,19mi,20,62,68mi,69 | 51430 |
| Khasra | Village Mirzapur 179mi, 180mi, 181mi,182mi, 183mi,184mi,185,186,187,188,190mi,191mi,194,196mi,198mi,200mi,201,203mi,204,205mi,206mi,207,208,467mi,468,469,470,471,472,473,474,475, 476,477,478,480,481,483,484,486,487,488,489,490,491 | 48170 |
| Khasra | Village Manbela 697, 699, 688mi, 691mi, 693, 694, 700, 679, 701, 702, 703, 704, 705, 706,707mi,716mi,717mi, 719mi,720mi, 678, 675, 673, 670, 591, 546mi, 547, 548, 549, 551, 554mi, 561mi, 563mi, 565, 567mi, 553mi, 568mi, 569mi, 570mi, 571mi,572,573,575mi,576,577mi,580,581mi,898mi,878mi,880 | 408810 |
Development Works
| work_name | description |
|---|---|
| Demarcation of Plots | We have developed a 207 acres township. The existing one side is 30 mtr wide, and the other is also 30 mtr wide. |
| Boundary Wall | 1.80m high and 115mm thick brick work and RCC work in column and beam. |
| Road Work | We have provided 30 mtr/ 24mtr/18mtr/12mtr/9mtr/7.5 mtr and 6 mtr of RCC road throughout the project. |
| Footpaths | We have provided an 80mm thick paver block at footpath over 100mm thick hardcore. |
| Water Supply Including Drinking Water Facilities | We have provided water supply from store at UGT and pneumatic pump and further distribute through under ground pipelines. |
| Sewer System | Modular sewarage system shall be provided. All sewarage water shall go to the STP and overflow from the STP shall be connected irrigation line and flushing line. The excess overflow is connected to the Municipal sewarage system, when comes into the system. |
| Drain | The stormwater from the road and other landscapes areas will connect with the drain channel and go to the RWH pit to recharge the groundwater and overflow shall be connected with the municipal drain line when comes in the system. |
| Parks | We will provide a landscape, kids play zone, and pedestrian tracks, seating benches,etc. |
| Tree Planting | We will provide many types of trees all along the boundary wall and green areas. |
| Design For Electric Supply Including Street Lighting | We will design and implement the system as per UPPCL and we will consider a centralized transformer, HT panel, LT panel, Feeder Pillar, and DG back for common serives like External Water supply,STP,pump room etc. |
| Community Buildings | N/A |
| Treatment and Disposal System of Sewage and Sullage water | All sewarage water shall go to the STP and overflow from the STP shall be connected irrigation line and flushing line. |
| Solid Waste Management And Disposal System | There are a proper garbage collection area provided for the solid waste management. |
| Water Conservation System | We will suggest that individuals use low flow fixtures as well as dual flash cisterns and raw water harvesting system to reduce waqter consumptions and improve |
| Energy Management System Including Use of Renewable Energy | We will use LED lights fitting in external area as well as solar lights. in pump room also all the equipmen shall have energy efficient motor. And we will suggest to individual also to use. |
| Fire Protection And Fire Safety System | We will provide fire figting facility in common ares while individual owner can install their own system as per their and local authorities requirement. |
| Social Infrastructure And Other Public Amenities Including Public Health Services | N/A |
| Emergency Evacuation Services | We can proposed Emergency Evacuation Services and fix sinage for the same system. |
| Other Miscellaneous Work | N/A |
Bank Details
| Bank Name | ICICI BANK |
| Branch | ICICI BANK LTD TARAMANDAL ROAD GORAKHPUR |
| Branch Address | DEORIA BYPASS ROAD TARAMANDAL GORAKHPUR |
| Account Holder | GDA RERA COLLECTION AC FOR RAPTI NAGAR VISTAR TOWNSHIP AND SPORTS CITY YOJNA |
| Account Number | 740905000993 |
| IFSC Code | ICIC0007409 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in