Centre Point Complex
Skylandvision Infra Private Limited
Lucknow, Uttar Pradesh
Approved
1st Jun 2022
Completed
30th Dec 2024
Registration No.
UPRERAPRJ398937
Project Type
Commercial
District
Lucknow
Taluka
Sarojini Nagar
State
Uttar Pradesh
Project Details
| RERA ID | UPRERAPRJ398937 |
| Project Status | Completed |
| Project Category | Commercial |
| District | Lucknow |
| Taluka | Sarojini Nagar |
| Start Date | 2022-06-01 |
| Completion Date | 2024-12-30 |
| Total Area (sqm) | 1802 |
| Project Cost (Lacs) | 500 |
| Duration (Months) | 31 |
| Registration Fee | 15800 |
Promoter Details
| Promoter Name | Skylandvision Infra Private Limited |
| Promoter ID | UPRERAPRM177677 |
| Mobile | 93******** |
Project Team
| role | name |
|---|---|
| Architect | Ravi Kant Dubey |
| Contractor | Skylandvision Infra Private Limited |
| Structural Engineer | Chaudhary Mohammed Nadeem |
Land Details
| type | khasra_or_plot_no | area_sqmt |
|---|---|---|
| Plot | GGCP-COM-M2-B | 1801.97 |
Unit Configuration
| Block No | Floor Number | Flat/ Apartment/ Shop/Plot type | Number of Apartment/Flats/Shop | Unit Carpet Area (in sqm) | Open Parking Space (in Nos.) |
|---|---|---|---|---|---|
| Centre Point Complex | BSMNT | SHOP | 5 | 336 | - |
| Centre Point Complex | 1 | SHOP | 5 | 478 | - |
| Centre Point Complex | 2 | SHOP | 6 | 531 | - |
| Centre Point Complex | 3 | OTHER | 1 | 775 | - |
| Centre Point Complex | BSMNT2 | OTHER | 0 | 900 | - |
Development Works
| work_name | description |
|---|---|
| Demarcation of Plots | Demarcation of plot GGCP-COM-M2-B-situated at EMAAR MGF integrated township already done before starting of project. |
| Boundary Wall | Boundry wall work already done. Northern wall is 48.55 mt, Eastern is 15.19 mt, Western is 21.90 mt and southern is 58.38 mt. Size of the wall is 5.6 ft (height) and width is 9 inch. Remaining work will be done before completion. |
| Road Work | Since the project is at the corner their is no need to develop road at site, however, wears n tears (if any) will be done after completion. |
| Footpaths | Project is at T-End of the road i.e, at the corner. No specific footpath required to be done. Building foothpath will be done before completion.. |
| Water Supply Including Drinking Water Facilities | Water supply available from "Jal Kal" department and also we will install tank of 25K Gallon at the roof top as back-up. |
| Sewer System | Sewer system already available by Lucknow Muncipality Corporation - LMC. |
| Drain | Water drain system will be developed as water supply and drain plan. |
| Parks | Since it is single commercial building supposed to be developed their is no park development required. |
| Tree Planting | Since it is single commercial building supposed to be developed their is no specific "Tree Planting" required. We will work on tree planting near parking and indoors. |
| Design For Electric Supply Including Street Lighting | We plan to have proper lightning inside building as per electrical plan. Also, we will arrange power back-up 24X7 as back-up. Additionally, we will work with relevant government departments to maintain existing street lights. |
| Community Buildings | Project is commercial in nature their is no requirement of community building. |
| Treatment and Disposal System of Sewage and Sullage water | We plan to have robustic treatment and disposal system of sewage and sullage water as per plan. |
| Solid Waste Management And Disposal System | We will develop solid waste management and disposal system as per attached plan. |
| Water Conservation System | We are working with our engineers and see how well we can conserve water. |
| Energy Management System Including Use of Renewable Energy | No applicable. |
| Fire Protection And Fire Safety System | We will install "Fire protection and fire safety system" as per standard norms by the fire department during the development of project. |
| Social Infrastructure And Other Public Amenities Including Public Health Services | Since our project is commercial in nature their is no need for amenities. We will keep all hygiene and human health safety protocols up and running. after completion. |
| Emergency Evacuation Services | Emergency evacuation plan prepared and we will make sure that in case of emergencies fire alarm and clear staircase remain available. We will work with stakeholders on tenant training on evacuation. |
| Other Miscellaneous Work | Work-In-Process. |
Bank Details
| Bank Name | Jammu and Kashmir Bank |
| Branch | Akbari Gate Crossing |
| Branch Address | Abdulaziz Road, Akbari Gate Crossing |
| Account Holder | Skylandvision Collection Account for Centre Point Complex |
| Account Number | 0328010100002019 |
| IFSC Code | JAKA0LUKNOW |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in