Construction of 144 nos Flats ( G+3) under PM Avas Yojna at Sec-15 Majhola Yojna No-4, Ph-2 (Vistar) Moradabad
U.P. Awas Evam Vikas Parishad
Moradabad, Uttar Pradesh
Approved
4th Jun 2020
Completed
3rd Sept 2024
Registration No.
UPRERAPRJ685451
Project Type
Residential
District
Moradabad
Taluka
Moradabad
State
Uttar Pradesh
Project Details
| RERA ID | UPRERAPRJ685451 |
| Project Status | Completed |
| Project Category | Residential |
| District | Moradabad |
| Taluka | Moradabad |
| Start Date | 2020-06-04 |
| Completion Date | 2024-09-03 |
| Total Area (sqm) | 1227 |
| Project Cost (Lacs) | 742 |
| Duration (Months) | 51 |
| Registration Fee | 11500 |
Promoter Details
| Promoter Name | U.P. Awas Evam Vikas Parishad |
| Promoter ID | UPRERAPRM4243 |
| Mobile | 87******** |
Project Team
| role | name |
|---|---|
| Architect | Mukesh Ruhela |
| Contractor | UP AVAS VIKAS PARISHAD |
| Structural Engineer | SANJAY JAISWAL |
Land Details
| type | khasra_or_plot_no | area_sqmt |
|---|---|---|
| Khasra | 308 | 950 |
| Khasra | 307 | 1910 |
Unit Configuration
| Block No | Floor Number | Flat/ Apartment/ Shop/Plot type | Number of Apartment/Flats/Shop | Unit Carpet Area (in sqm) | Open Parking Space (in Nos.) |
|---|---|---|---|---|---|
| 1 | 1 | 1 BHK | 12 | 22.77 | - |
| 1 | 2 | 1 BHK | 12 | 22.77 | - |
| 1 | 3 | 1 BHK | 12 | 22.77 | - |
| 1 | 4 | 1 BHK | 12 | 22.77 | - |
| 2 | 1 | 1 BHK | 12 | 22.77 | - |
| 2 | 2 | 1 BHK | 12 | 22.77 | - |
| 2 | 3 | 1 BHK | 12 | 22.77 | - |
| 2 | 4 | 1 BHK | 12 | 22.77 | - |
| 3 | 1 | 1 BHK | 12 | 22.77 | - |
| 3 | 2 | 1 BHK | 12 | 22.77 | - |
| 3 | 3 | 1 BHK | 12 | 22.77 | - |
| 3 | 4 | 1 BHK | 12 | 22.77 | - |
Development Works
| work_name | description |
|---|---|
| Demarcation of Plots | The Plot is clearly demarcated in Sector 15 in Majhola No-4 (vistar) Moradabad as per the sanctioned layout the plot is situated facing 9.00 m wide road in layout. Apart from 12.00 m wide road and 6.00 m wide road are also proposed in layout encompassing this plot. |
| Boundary Wall | Boundary wall is not included in the proposed projected. It will be constructed seprate project. |
| Road Work | Road work for the whole scheme is sanctioned and tender processing is running for construction. In the proposed project of 144 Nos. of houses 6.00 meter wide road, 7.50 meter wide road 9.00 meter wide and 3.00 meter CC tiles road along two side periphere which is shown in layout is to be constructed as seperate project. |
| Footpaths | Footpaths are not proposed in the sanctioned layout plan of the project. |
| Water Supply Including Drinking Water Facilities | Over head tank and Water supply distribution system is sanctioned and tender proceesing is running for cosntruction this project which will be done at completion stage as seperate project. |
| Sewer System | Sewer distribution system is sanctioned and tender proceesing is running for cosntruction this project which will be done at completion stage as seperate project trunk sewer line is laid alreay. |
| Drain | Drainage system of whole scheme are in under project which is likely to be completed November 2020. Internal drain. |
| Parks | Construction of boundary wall/RCC grill of the proposed park in the scheme is sanctioned and tendering is processing. Plantation work is already completed wire fencing is already completed. |
| Tree Planting | Tree plantation in the scheme is under progress which will be done on roads and parks of the scheme. For the mentioned plot of PMAY 144 Nos. of houses plantation on 7.50 m and 9.00 m wide road and 6.00 m wide road will be done after drain and road work. |
| Design For Electric Supply Including Street Lighting | Electric supply including street lighting is not included in the proposed projected. It will be constructed seprate project. |
| Community Buildings | Community building is proposed in layout of Sector 15 in Majhola No-4 (vistar) Moradabad. Which is not too far away from this project. |
| Treatment and Disposal System of Sewage and Sullage water | Treatment and disposal system of sewage and sullage water is proposed in yojna layout Sector 18 in Majhola No-4 (vistar) Moradabad. Which is not too far away from this project. |
| Solid Waste Management And Disposal System | Solid waste management and disposal system is proposed in layout Sector 15 in Majhola No-4 (vistar) Moradabad. Which is not too far away from this project. |
| Water Conservation System | In the presence proposed PMAY housing scheme unit area of individual flat is very small thus water conservation system is not the part of this project. |
| Energy Management System Including Use of Renewable Energy | n the present proposed PMAY Housing scheme energy management system including use of renewable energy is not proposed in the approved DPR. |
| Fire Protection And Fire Safety System | In the present proposed PMAY Housing scheme Fire proctetion and fire safety system is not the part of approved DPR. |
| Social Infrastructure And Other Public Amenities Including Public Health Services | Public Amenities such as schools, hospitals etc are available in nearby vicinity |
| Emergency Evacuation Services | Sufficient No of staircases is being proposed in the building |
| Other Miscellaneous Work | Ample amount of open areas park etc are available in Sector 15 in Majhola No-4 (vistar) Moradabad. |
Bank Details
| Bank Name | Induind Bank |
| Branch | Sai Tower Near Ekta Dwar |
| Branch Address | Civil Lines Moradabad |
| Account Holder | Executive Engineer UPAVP Moradabad |
| Account Number | 150733734735 |
| IFSC Code | INDB00001551 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in