DEWAN ENCLAVE
Joginder Gandhi
Moradabad, Uttar Pradesh
Approved
9th Jan 2023
Completed
31st Aug 2025
Registration No.
UPRERAPRJ432084/02/2024
Project Type
Residential
District
Moradabad
Taluka
Moradabad
State
Uttar Pradesh
Project Details
| RERA ID | UPRERAPRJ432084/02/2024 |
| Project Status | Completed |
| Project Category | Residential |
| District | Moradabad |
| Taluka | Moradabad |
| Start Date | 2023-01-09 |
| Completion Date | 2025-08-31 |
| Total Area (sqm) | 7687 |
| Project Cost (Lacs) | 244 |
| Duration (Months) | 32 |
| Registration Fee | 43500 |
Promoter Details
| Promoter Name | Joginder Gandhi |
| Promoter ID | UPRERAPRM219880 |
| Mobile | 98******** |
Project Team
| role | name |
|---|---|
| Architect | SANJEEV KUMARZ |
| Contractor | MEHAR CONSTRUCTIONS |
| Structural Engineer | NAZIM ALI |
Land Details
| type | khasra_or_plot_no | area_sqmt |
|---|---|---|
| Khasra | 793,794,795,796,797,798 | 12980 |
| Khasra | 793,794,795,796,797,798 | 10859 |
Development Works
| work_name | description |
|---|---|
| Demarcation of Plots | DEMARCATION OF PLOTS IS DONE THROUGH BRICK WORKS OF 4.5 INCH IN ZIG-ZAG PATTERN. |
| Boundary Wall | EXISTING BOUNDARY WALLS OF 6 FEET HEIGHT AND 9 INCH THICK THROUGH BRICK WORK AND FOUNDATION BRICK WORK OF 4 FEET UNDER THE GROUND STARTING WALL FOUNDATION FRO 22INCH THICKNESS GOING UP TO 18 INCH AND THEN 14 INCH AND FINALLY 9 INCH AND COLUMN IN BRICK BOUNDARY WALL AND PLASTER WORK IN INNER SIDE AND PLASTER WORK IN FRONT BOTH SIDE. |
| Road Work | 9METER INTERNAL ROAD WILL BE MADE BY RAMMED EARTH AND THEN 150MM WBM 40-63 STONE/BAJRA AND THEN 150 MM THICK PCC AND THEN 125 MM THICK CONCRETE/RCC. |
| Footpaths | WILL BE MADE BY RAMMED EARTH AND THEN 100 MM WBM 40-63 STONE/BAJRA AND THEN SAND WORK AFTER THAT PAVERS WILL BE INSTALLED. |
| Water Supply Including Drinking Water Facilities | WATER SUPPLY SHALL BE DONE TILL PARK AREA DRINKING WATER FACILITY TO BE DONE BY RESIDENTS. |
| Sewer System | SEWER SYSTEM WILL BE MADE UNDER GROUND WHICH CONSIST BY RAMMED EARTH AND THEN 100MM THICK PCC AND THEN HDPE PIPES DOUBLE WALL AND THEN PCC. |
| Drain | DRAIN WILL CONSIST OF HDPE PIPE DOUBLE WALL AND MAIN HOLES IN REGULAR INTERVAL. |
| Parks | WATER BDIES/LANDSCAPE AND KIDS PLAY AREA ALONG WITHGREEN AREA WOULD BE DEVELOPED. |
| Tree Planting | THE TREES WILL BE PLANTED AT ALL SUITABLE LOCATIONS OF THE PROJECT AND ALONG THE BOUNDARY WALL. |
| Design For Electric Supply Including Street Lighting | ELECTRICAL LAYOUT AND CAPACITY WILL BE INSTALLED TO SUFFICE THE RESIDENTIAL USE . ALL ELECTRICAL CABLING WILL BE UNDERGROUND AND STREET LIGHTS WILL BE AS PER WORKING DRAWINGS. ELECTRICITY SUPPLY SHALL BE DONE THROUGH IRON POLES AS PER THE ELECTICITY PLANS. |
| Community Buildings | NA |
| Treatment and Disposal System of Sewage and Sullage water | ALL WASTE OF SEWER LINE TO BE COLLECTED AT STP, AFTER TREATMENT WATER TO BEUSED FOR WATERINGOF THE GREEN AREA, RWH LINE IS PLANNED TO COLLECT WATER FROM DRAINAND TO BE DIRECTED TO MULTIPLE RECHARGE PITS, IRIIGATIONOF PLANT BY FLUSH-WATER SYSTEM, AS PER LAYOUT. STANDARD STP SYSTEM WITH 40KLD |
| Solid Waste Management And Disposal System | ALL WASTE OF SEWER LINE TO BE COLLECTED AT STP, GARBAGE COLLECTION TO BE DONE THROUGHAUTHORISED AGENCY AND TO BE DISPOSED AT GARBAGE DISPOSAL AREA AS PER SANCTION PLAN. OR STP/COMPOSTING PIT |
| Water Conservation System | RAIN WATER HARVESTING LINE TO BE LAID , IRRIGATION OF PLANT BY FLUSH- WATER SYSTEM, AS PER SANCTIONED LAYOUT RWH LINE IS PLANNED TO COLLECT WATER FROM DRAIN AND TO BEDIRECTED TO MULTIPLE RECHARGE PITS, IRRIGATION OF PLANT BY FLUSH WATER SYSTEM AS PER LAYOUT. . |
| Energy Management System Including Use of Renewable Energy | NA |
| Fire Protection And Fire Safety System | NA |
| Social Infrastructure And Other Public Amenities Including Public Health Services | NA |
| Emergency Evacuation Services | NA |
| Other Miscellaneous Work | NA |
Bank Details
| Bank Name | State Bank Of India |
| Branch | STATE BANK OF INDIA |
| Branch Address | Specialiazed Commercial Branch, Civil Lines, Moradabad |
| Account Holder | Surender Gandhi Joginder Gandhi Collection Account for Dewan Enclave |
| Account Number | 41632900474 |
| IFSC Code | SBIN0004113 |
The information provided on this page is collated from publicly available resources. PropTech Pulse does not guarantee the accuracy, completeness, or authority of this data and shall not be held liable for any discrepancies. For queries or further assistance, please contact us at pulse@aurumproptech.in