Trial runs have commenced on the Phase 2A section of Bengaluru Metro's Blue Line along the Outer Ring Road (ORR), starting from KR Puram. The testing began on Tuesday, November 24, 2026, across the first four stations towards Mahadevapura.
Public operations on the corridor are targeted for mid-2027, Greater Bengaluru Development Minister Krishna Byre Gowda said.
The minister inspected the progress at Doddanekkundi Metro Station. The trials will progressively extend to other stations in the coming weeks.
The 19-km Phase 2A corridor connects KR Puram with Central Silk Board and includes 13 stations. The testing schedule includes:
According to the minister, automatic signalling installation is still pending. The work is expected to be completed by January, with mandatory safety certification scheduled to begin after February.
The testing and certification process is expected to take another seven to eight months before the corridor opens to passengers.
Also Read: Bengaluru Metro Pink Line Gets Safety Clearance
The complete Blue Line project will cover approximately 58.2 km, connecting Central Silk Board through KR Puram and Hebbal to Kempegowda International Airport. It is being implemented at an estimated cost of around ₹20,000 crore.
The project is divided into two phases:
Gowda said the government was directing officials to accelerate work on Phase 2B by coordinating with contractors.
He particularly highlighted the KR Puram-Hebbal stretch, where construction progress needs to improve.
The government is targeting completion of the entire Blue Line corridor within the next one-and-a-half years, according to the report.
Also Read: Bengaluru Pink Line: Real Estate Along 7.5-km Metro Route
Gowda said the state government was ensuring that funding constraints did not affect ongoing Metro projects.
The state bears loan repayment responsibilities and provides financial assistance to meet the operating losses of the Metro corporation.
He also pointed to foreign exchange fluctuations, saying the dollar had increased from around ₹70–₹80 at the time of borrowing to approximately ₹100. This had added nearly 30% to the loan repayment burden.
Delays in project approvals had also increased construction material costs and overall expenditure, he said.
Other Metro proposals discussed by the minister included:
The minister also clarified that no decision had been taken to increase Metro ticket fares.
He said comparisons with other Metro systems should consider differences in government support, network length and passenger volumes.