The Haryana Real Estate Regulatory Authority (HRERA) has ruled that homebuyers who choose to remain in a delayed housing project and receive interest for delayed possession cannot claim separate compensation for the same delay.
The decision came while dismissing a ₹91 lakh compensation complaint filed by two Delhi-based buyers against Anand Divine Developers, the developer of ATS Triumph in Gurugram.
Adjudicating Officer Rajender Kumar dismissed the complaint on November 11, 2026.
He noted that the buyers had already secured relief from HRERA in an earlier order dated September 28, 2023, which directed the developer to pay interest at 10.7% per annum for the possession delay.
The buyers, Dr Renu Srivastav and Col (Dr) Ashwini Goel, had booked unit 6031 in Tower 6 under an agreement signed on March 27, 2018.
The apartment was priced at ₹1.9 crore, while their total payment was approximately ₹2.2 crore, including a bank loan of ₹1.56 crore.
They subsequently sought compensation under several heads, including rental expenses, mental harassment, interest and litigation costs.
Their claims included ₹45.4 lakh with 18% interest, monthly rent of ₹1.2 lakh and ₹25 lakh for alleged harassment.
Also Read: Gurugram RERA Approves 51 Projects Worth ₹38,000 Crore
The adjudicating officer referred to Section 18(1) of the Real Estate (Regulation and Development) Act, 2016, and previous tribunal decisions.
The interpretation applied in this case distinguishes between buyers who withdraw from a delayed project and those who continue with their allotment.
The officer held that allowing additional compensation for the same possession delay, after interest had already been awarded, would amount to granting overlapping relief.
The order referred to the Uttar Pradesh Real Estate Appellate Tribunal's decision in Greater Noida Industrial Development Authority versus Ranjan Misra and the Haryana tribunal's February 2026 ruling in Tata Housing versus Nitin Singhal.
The buyers had also raised issues involving carpet and terrace area, missing wooden flooring, an electricity meter, seepage and pending paintwork.
The officer did not entertain these allegations because they had not been pleaded before the Authority in the earlier proceedings. The order noted that violations must first be established through the appropriate process.
Also Read: Haryana RERA Grants 4-Month Extension for West Asia Impact
The decision highlights the importance of understanding the remedies available under RERA before filing a compensation claim.
Homebuyers facing delayed possession should distinguish between statutory interest for delay, withdrawal and refund rights, and claims arising from separate construction or agreement violations.
For developers, the ruling reinforces the need to comply with possession timelines and statutory interest directions.
It also clarifies that a buyer's decision to continue with a project can affect the type of relief available for the same delay.
Developers must still meet their obligations under the RERA Act and the applicable sale agreement.
For the Gurugram residential market, consistent application of RERA provisions can improve clarity around buyer-developer disputes and possession-related liabilities.
Greater clarity may help homebuyers assess their legal options and encourage developers to address delays and documented construction deficiencies.
However, the decision concerns the specific complaint and does not mean that every homebuyer who accepts possession automatically loses all rights to compensation.
Separate violations and claims may require independent proceedings and examination under the relevant provisions of the law. Buyers should review the facts, previous orders and applicable legal remedies before deciding how to proceed.